Compare two estimates without double-counting
Use a line-item crosswalk to separate quantity, scope and pricing differences.
General educational information. Not a site-specific safety, coverage, licensing or legal determination.
1. Set up a comparison row
Use one row per disputed item: location | original line and version | proposed line | unit and quantity | difference | evidence | open question.
2. Normalize the units
Convert to a common unit without turning a measured quantity into an installed quantity. Document waste, rounding and deductions separately so a reviewer can replay the math.
3. Check for overlap
A task may appear once as part of an assembly and again as a separate line. Compare descriptions and scope before calling it omitted.
4. Write a neutral conclusion
Example: one estimate has 80 linear feet and the field record shows 96. Identify the additional 16 feet on the sketch, note assumptions and leave pricing and coverage questions separate.
A question worth asking
Is the difference in work, measurement, price or how the same work was grouped?